# ERCOT Plan Could Limit Power at Riot’s Texas Bitcoin Mine

By John Kim

Canonical URL: https://www.tokenpost.com/news/business/64556
Published: 2026-11-29T15:17:06.000Z
Updated: 2026-11-29T15:17:06.000Z
Section: Business

> The grid operator can impose group limits when combined demand reaches roughly 2,500 megawatts, even if Texas has unused capacity.

Riot Platforms’ Corsicana Bitcoin (BTC) mine could face limits on its electricity use if other computing sites in the same monitored group increase demand on the Texas grid operated by the Electric Reliability Council of Texas (ERCOT).

ERCOT plans to activate group limits when combined demand reaches roughly 2,500 megawatts. The shared operating ceiling is 2,720 megawatts, below the 3,200 megawatts of demand ERCOT modeled could disappear suddenly during a transmission fault.

ERCOT can activate limits for the transmission providers and market schedulers responsible for the sites, constraining how much power Corsicana and other facilities can draw. The restriction could affect Riot even if its own electricity use remains unchanged.

The monitored group’s sites reached a simultaneous draw of 1,615 megawatts in September while holding approvals for 5,465 megawatts. ERCOT assigns shares based on recent consumption, so additional computing demand could narrow the remaining capacity before sites reach their individual approved amounts.

Riot’s existing Corsicana operations qualify for an exemption from newer requirements to remain connected during voltage and frequency disturbances. Corsicana is still part of a group monitored under ERCOT’s plan, which had not been activated when Riot filed its quarterly report.

The limits are designed to reduce the risk that multiple computing sites disconnect at the same time after a transmission fault. ERCOT modeled a scenario in which the sudden loss of 3,200 megawatts of demand could push grid frequency to 60.4 cycles per second under certain conditions, increasing the risk that outages could spread.

Cryptocurrency miners also remain a source of flexible demand for the Texas grid. During Winter Storm Fern in January 2026, miners reduced demand by an estimated 4,100 megawatts, nearly 5% of ERCOT’s forecast peak demand. Oil and gas operators cut about 4,200 megawatts, while steelmakers reduced demand by about 420 megawatts and data centers by 170 megawatts.

Riot booked about $24.7 million in power credits during the third quarter through power sales and demand-response programs. The company can voluntarily reduce electricity use at some facilities.