# Keel Infrastructure Ends U.S. Bitcoin Mining to Expand AI Data Centers

By John Kim

Canonical URL: https://www.tokenpost.com/news/business/64583
Published: 2026-11-29T17:12:35.000Z
Updated: 2026-11-29T17:12:35.000Z
Section: Business

> The former Bitfarms sold 2,261 BTC from its treasury and 259 BTC from operations for $192.2 million, while targeting 1,928 megawatts of data-center capacity.

Keel Infrastructure has sold 2,261 Bitcoin (BTC) from its treasury and 259 BTC produced by its operations for $192.2 million as the former Bitfarms shifts its infrastructure strategy toward artificial intelligence data centers.

The company has ended Bitcoin mining at its U.S. facilities and plans to sell Bitcoin produced by its remaining facilities on a daily basis.

Keel held $780 million in liquidity as of Nov. 4 and plans to expand its data-center infrastructure to 1,928 megawatts. The sale comprised 2,261 BTC from the company’s treasury and 259 newly mined BTC.

The shift comes as mining economics face pressure. On Nov. 29, the Electric Floor Cost indicator stood at $61,944, above Bitcoin’s price of about $59,274. The measure represents the theoretical electricity cost of mining Bitcoin.

Bitcoin was down 55% from its peak during the current cycle. Previous major declines included 93% in 2011, 85% from 2013 to 2015, 77% in 2018 and 73% during the 2022 FTX and Terra crash.

Keel’s next stated step is to continue selling Bitcoin produced at its remaining facilities while pursuing its artificial intelligence data-center strategy.