# U.S. Data Center Starts Fell 28% in Q3, Then Rebounded in October

By Simon Yoon

Canonical URL: https://www.tokenpost.com/news/technology/60527
Published: 2026-11-18T14:38:14.000Z
Updated: 2026-11-18T14:38:14.000Z
Section: Technology

> Developers began work on 8.4 gigawatts of capacity across 65 buildings in Q3. October starts reached 4.6 gigawatts, the series’ second-highest monthly total.

U.S. data center construction starts dropped 28% in Q3 2026 after a record quarter, then rose in October, leaving the pace of the buildout in question.

Developers began construction on buildings representing 8.4 gigawatts (GW) of power capacity across 65 buildings from July through September, down from 11.7 GW across 96 buildings in April through June. The decline was the first quarterly drop in more than a year. Even so, Q3 was the third-highest quarter in the series and stood 55% above the same period in 2025.

A start is counted in the month vertical construction begins, identified through satellite imagery showing foundation and steel work. The measure tracks power capacity at the start of vertical construction, not completed capacity or actual electricity consumption.

October starts reached 4.6 GW, nearly twice the October 2025 total and the second-highest monthly figure in the series. Three highlighted October starts totaled 1,631 megawatts (MW), about 35% of the monthly total: Nscale’s 720-MW Monarch campus in West Virginia, Related Digital’s 461-MW Stargate Michigan campus and Crusoe’s 450-MW Abilene campus in Texas.

The tally spans hyperscale and colocation facilities, enterprise data centers and crypto mines, so it does not isolate AI projects. The wider U.S. buildout has also faced [labor and permitting pressures](<https://www.tokenpost.com/news/technology/24428>).

The estimated cost to build and equip U.S. data centers that have started construction so far in 2026 is about $1 trillion. “A lasting slowdown would reach the utilities planning new power plants, the companies making chips and turbines, and a stock market that has bet heavily on AI,” Michael Thomas, Cleanview’s founder and CEO, wrote.

In the 12 months through October, starts totaled 38 GW, while 58 GW was under construction and 65 GW was operating. Thomas wrote that “one month doesn’t make a trend.” If starts in November and December match October’s total, Q4 could reach about 14 GW and set a record.