# FC-BGA Equipment Lead Times Stretch to 30 Months Amid AI Demand

By Simon Yoon

Canonical URL: https://www.tokenpost.com/news/technology/63251
Published: 2026-11-27T05:15:08.000Z
Updated: 2026-11-27T05:15:08.000Z
Section: Technology

> Manufacturers are submitting letters of intent and making advance payments as shortages of Japanese precision components delay equipment used to produce advanced substrates.

Some equipment used to produce flip-chip ball-grid array (FC-BGA) substrates now has lead times of about 30 months, up from roughly six months, as artificial intelligence chip demand strains upstream manufacturing capacity.

Substrate manufacturers are submitting letters of intent before placing purchase orders and making advance payments to reserve equipment. Only a limited number of manufacturers have received firm delivery commitments.

Unimicron said Oct. 27 that its board approved an additional NT$50.9 billion in long-lead-time equipment pre-orders. The increase was the company’s fourth this year and its largest single increase.

The longer lead times are mainly linked to limited supplies of precision motors, drive components, servomotors and controllers from Japan. A manufacturer of FC-BGA bonding equipment said components that were previously readily available now require about six months to arrive.

The delays add uncertainty to planned substrate capacity expansions across Japan, South Korea and Taiwan. Equipment ordered in November 2026 could arrive as early as mid-2029, making delivery schedules and component availability key constraints for manufacturers trying to expand output.

FC-BGA substrates are used in advanced chip packages, including packages designed for high-performance computing. The supply pressure reflects how demand for AI-related semiconductors is extending beyond chips into the materials and equipment needed to manufacture them.