Star Diamond Posts C$872,000 Q3 Loss as Financing Delays Study
Cash stood at C$73,000 on Sept. 30. The company estimates C$2.863 million in remaining study costs and about 12 months of work after financing and contractor scheduling.

Star Diamond Corporation reported an unaudited net loss of C$872,000 for the three months ended Sept. 30, as a financing shortfall delayed a pre-feasibility study for its Saskatchewan project and cash stood at C$73,000.
The quarterly loss was lower than the C$989,000 recorded in the same period of 2025. Loss per share was C$0.00 in both quarters, rounded to the nearest cent. The company’s results table displayed a dash for revenue in each quarter.
For the first nine months of 2026, Star Diamond recorded a net loss of C$3.021 million, compared with C$3.405 million in the same period a year earlier. Loss per share was C$0.00, rounded to the nearest cent, versus C$0.01 in 2025.
Cash declined from C$724,000 on Dec. 31, 2025, to C$73,000 on Sept. 30. The company also moved from C$458,000 in working capital at year-end to a C$1.097 million working-capital deficit at the end of September.
Star Diamond said it needs more financing to continue as a going concern. It warned that if it cannot raise funds on time, that could cause it to suspend operations and planned activities.
The company has delayed work on a pre-feasibility study for the Star – Orion South Diamond Project in Saskatchewan. The project site is under care and maintenance. Star Diamond describes itself as a Canadian natural-resources company focused on mineral exploration and development.
The remaining study work is estimated to cost about C$2.863 million. The company had set a total study budget of C$3 million and estimated that about C$137,000 had been spent to date.
Star Diamond estimates the study will take about 12 months to complete after financing is secured, contractors are scheduled and work resumes. The schedule depends on all three conditions being met.