Texas Record Lists $1.3 Billion Data Center Project at Core Scientific Site
The 341,326-square-foot project is scheduled to start construction Nov. 24. AMD has leased about 110 megawatts of capacity, with initial delivery expected in the first half of 2028.

Core Scientific’s Hunt County, Texas, site is slated for a $1.3 billion data center build, extending the company’s shift toward artificial intelligence (AI) and high-performance computing (HPC) hosting.
A project entry dated Friday, Nov. 13, at the Texas Department of Licensing and Regulation (TDLR) lists Telios Quinlan One, LLC as the owner. The planned facility spans 341,326 square feet and carries an estimated cost of $1.3 billion. Core Scientific acquired the site in May for $232.5 million in cash.
Advanced Micro Devices (AMD) has leased about 110 megawatts of capacity at the site, with initial delivery expected in the first half of 2028. That delivery window precedes the project’s scheduled completion date of Sept. 4, 2028.
Core Scientific had 485 megawatts of colocation capacity under billing as of Sept. 30, up from 395 megawatts at the end of June. That capacity represented more than $700 million in average annualized colocation revenue under generally accepted accounting principles. Colocation generated $215.4 million of the company’s $232.9 million in third-quarter revenue, or about 92%. Revenue from the business was about $137 million in the second quarter and $15 million a year earlier. The third-quarter revenue results show how central hosting has become to the company’s business.
Bitcoin (BTC) mining generated 7.5% of Core Scientific’s third-quarter revenue. The company plans to end its own mining operations by Dec. 31, 2026, then focus on AI and HPC hosting from 2027, as set out in its mining exit plan.
Construction is scheduled to begin Tuesday, Nov. 24, and finish Sept. 4, 2028.