Axe Compute Cash Rises to $147.7 Million as Contract Liabilities Jump

The GPU-as-a-Service company spent $349.6 million on Build cluster equipment, while all third-quarter revenue came from its Access service.

Cooling units stand outside a low industrial data center / TokenPost.ai
Cooling units stand outside a low industrial data center / TokenPost.ai

Axe Compute (NASDAQ: AGPU) ended the third quarter with $147.7 million in cash and equivalents, up from $21.9 million three months earlier, as customer prepayments lifted contract liabilities to $569.3 million.

Contract liabilities tied to customer prepayments rose from $60.8 million at the end of the second quarter. The company spent $349.6 million during the third quarter on cluster equipment for Build projects. Those prepayments were primarily intended to support GPU infrastructure purchases.

All third-quarter revenue came from GPU compute services through Axe Compute Access. The company recognized no revenue from Build contracts during the quarter, despite the equipment spending. The results were disclosed Nov. 17.

Axe Compute has signed orders with more than $3 billion in total contract value this year. Once fully deployed, the orders are expected to support an annualized revenue run rate above $700 million. Management provided no formal financial guidance, and the projected run rate depends on completing those deployments.

The company bought its Georgia cluster for $124.4 million on Sept. 30. The facility has 2,304 NVIDIA B300 GPUs and is awaiting customer acceptance, with operations targeted for the fourth quarter. The customer contract term was extended to 2031.

Axe Compute previously estimated about $352.6 million in revenue over the Georgia contract’s life. Deployments of the Georgia cluster and a Build contract signed in July are expected to begin in the fourth quarter and continue through 2027.

The company also completed the sale of Helomics, leaving GPU-as-a-Service as its sole business. The Georgia cluster and the July Build contract are among the projects expected to begin deployment in the fourth quarter.