Hyperscale Data Projects $74.8 Million in Michigan Data Center Spending
The former Bitcoin miner sold its remaining 211 BTC as it weighs financing options and warns available funds may not cover obligations over the next 12 months.

Hyperscale Data expects to spend about $74.8 million from November through March on remaining infrastructure for its Michigan data center, while warning that available funds may not cover planned spending and obligations over the next 12 months.
The former Bitcoin miner sold its remaining 211 Bitcoin (BTC) for about $16 million, completing its exit from Bitcoin holdings. The sale has not resolved the company’s funding needs for the project.
Hyperscale Data had about $17 million in unrestricted cash and about $231 million in current liabilities as of Sept. 30. It recorded a net loss of roughly $62 million during the first nine months of 2026. The company’s financial conditions raise substantial doubt about its ability to continue operating.
The Michigan project would convert a former mining site into a data center for an unnamed California-based AI infrastructure provider. Hyperscale estimates construction and equipment costs at $122.1 million and had spent about $47.3 million through October.
Management is considering debt, equity, asset sales and other transactions to raise funding. The company’s program for selling common shares directly into the market is suspended.
Hyperscale expects to deliver the first 10 megawatts of capacity in December. Its agreement covers a 20-megawatt supply. The company has described the contract as potentially generating $1.2 billion in revenue, conditional on the customer exercising two additional five-year extensions after the initial 10-year term and Hyperscale fulfilling its contractual obligations.