Texas Restarts Data Center Permit Reviews as Governor-Elect Pledges Data Center Ban
The Texas Commission on Environmental Quality resumed reviews in mid-November after a state grid assessment, while Gina Hinojosa plans to ban approvals after taking office Jan. 19.

Texas has resumed environmental permit reviews for data centers after a September pause ordered by Gov. Greg Abbott, while Gov.-elect Gina Hinojosa plans to ban all approvals after taking office Jan. 19.
The Texas Commission on Environmental Quality (TCEQ) restarted its regular process in mid-November after Abbott’s office notified the agency that the Electric Reliability Council of Texas (ERCOT) had completed its collection of data on data centers’ effects on communities. TCEQ handles air-quality and construction-runoff permits for the facilities.
Hinojosa, who defeated Abbott on Nov. 3, has pledged to ban all data center approvals until the Legislature passes laws protecting Texans. She is scheduled to take office Jan. 19.
Abbott’s review began in August, when he asked the Public Utility Commission of Texas (PUCT) and ERCOT to examine data centers seeking grid connections. ERCOT delayed the interconnection-review process for large electricity users and designated it “Batch Zero.” Applications in the queue represented an estimated 474 gigawatts of electricity demand, a scale Abbott said could threaten the reliability and stability of the Texas power grid.
On Sept. 21, Abbott directed TCEQ to suspend all data center permits until the ERCOT review was complete. He also called for data centers to pay for their own electricity infrastructure, avoid using water needed by local communities and report their electricity and water consumption.
ERCOT is targeting Dec. 10 to submit two reports to PUCT. The reports are expected to include recommendations on which large electricity users of at least 75 megawatts should remain in Batch Zero, along with data on data centers’ water use, electricity demand and community effects.
PUCT is expected to discuss the reports at a public meeting Dec. 17. The current deadline for the Batch Zero study’s results is April 9, 2027, although ERCOT has indicated it will not meet that date and expects an extension.
Public Citizen criticized the permitting restart, saying the ERCOT assessment had not been released publicly and TCEQ had not explained how it would use the information in its reviews. The organization called for TCEQ commissioners to resign.
Abbott’s suspension was issued as a gubernatorial directive rather than a statute or law, meaning Hinojosa could seek to revoke or revise it after taking office. She will also be able to appoint members of PUCT and TCEQ when terms expire.