Oracle’s Project Jupiter Faces Pipeline Access and Permit Hurdles
The New Mexico AI campus would receive natural gas through a proposed 17.8-mile pipeline, while its revised fuel-cell design aims to cut nitrogen-oxide emissions by 92%.

Oracle’s Project Jupiter AI data center campus in New Mexico faces federal permitting requirements and a rejected state-land access request as its developers shift the project toward lower-emissions fuel cells.
The proposed Green Chile natural-gas pipeline would run about 17.8 miles through a 24-inch-diameter pipe and supply up to 400,000 dekatherms of gas per day to Green Chile Ventures for power generation at the campus in Doña Ana County.
The Federal Energy Regulatory Commission (FERC) required additional historic-preservation documentation and moved the pipeline application into a case-specific authorization process. FERC scheduled an environmental assessment for Sept. 4, 2026, with a federal authorization deadline of Dec. 3, 2026.
Separately, the New Mexico State Land Office rejected Energy Transfer’s request for a proposed 0.63-mile pipeline segment across state trust land. The decision affects a pipeline right-of-way request rather than establishing a dispute over Oracle’s data-center parcel.
“Applicants will need to find a route that does not include state trust lands,” said Joey Keefe, assistant commissioner of communications for the New Mexico State Land Office.
Oracle and Yucca Growth Infrastructure changed the proposed power system from gas turbines and diesel generators to Bloom Energy fuel cells. The revised design would reduce nitrogen-oxide emissions by about 92% compared with the January plan.
The redesigned power system is not expected to draw on municipal drinking-water supplies for electricity production or cooling the data halls.
“Our updated plan delivers reliable on-site power with a smaller environmental footprint and avoids using public drinking water for power generation or data center cooling,” said Mahesh Thiagarajan, executive vice president of Oracle Cloud Infrastructure.
Project Jupiter could create more than 4,000 construction jobs and support 1,500 ongoing direct positions. Its estimated annual economic impact is $384 million during construction and $113 million once the campus is operational.
The project includes commitments of $50 million for local water systems, $360 million for schools, infrastructure and local services, and $6.9 million for workforce development and community programs.
“Project Jupiter represents a once-in-a-generation opportunity for southern New Mexico,” Thiagarajan said.
Regulators and commenters raised concerns involving siting permissions, easements, air quality, cultural resources, water resources, wildlife and cumulative effects. The pipeline remains subject to environmental review and federal authorization, with the Dec. 3 deadline next on the schedule.