乌兰察布 Signed 109 Computing-Center Projects With More Than 25 GW of Contracted IT Power Capacity by Mid-October

The projects plan more than seven million racks. Twenty-two computing projects were under construction in 察哈尔高新区, with nearly 30,000 workers across sites.

Flatbed trucks carry server racks past unfinished data center buildings / TokenPost.ai
Flatbed trucks carry server racks past unfinished data center buildings / TokenPost.ai

乌兰察布 had signed 109 computing-center projects with more than 25 gigawatts (GW) of contracted IT power capacity by mid-October. The projects plan more than seven million racks.

In 察哈尔高新区, 22 computing projects were under construction at the same time, with nearly 30,000 workers across sites. In 巴音片区, four data centers were being built along the same roads. More than 10 long flatbed trucks, each tens of meters long, lined up there carrying hundreds of unopened server racks. Some construction crews aimed to finish one data-center building every three months.

Customers’ required delivery times have shortened. 胡兴赞, CTO of 远景 AI 智算中心, said customers previously accepted construction periods of 12 months, then nine months and six months. Current requests call for delivery in two or three months.

Builders are securing land earlier, building factories and purchasing large equipment in advance. Some power-distribution systems are assembled as modules at factories and connected after they reach project sites. That approach can cut installation time from 10 days to two.

An unnamed project lead said a missed contractual delivery date carries a penalty of 500,000 yuan per day, or 15 million yuan over a month.