Google Data Center Stoppages in Belgium, Virginia Highlight Local Permitting Risks

Wallonia officials halted work over an amended permit, while a Virginia judge ordered construction stopped after finding an open-meetings violation.

Idle excavators stand at a halted data center construction site / TokenPost.ai
Idle excavators stand at a halted data center construction site / TokenPost.ai

Google halted work at a data center in Belgium, while a Virginia judge ordered construction to stop at another campus within the same week, highlighting local permitting risks for the company’s cloud and AI infrastructure buildout.

Wallonia inspectors ordered about 300 workers to stop construction at Google’s Farciennes site on Nov. 26. The regional government said Google continued building after an amended permit was revoked in August.

Google said it paused work “pending additional guidance.” The company said its original permit for air-cooled facilities remains valid and that it remains “committed to complying with local laws.”

Wallonia Planning Minister François Desquesnes revoked the amended permit because of the project’s water demand and drought risk. Google had sought to combine two planned data centers into one larger facility cooled with water drawn from the River Sambre.

Greenpeace Belgium filed an urgent complaint after construction continued. Joeri Thijs of Greenpeace Belgium called the work “disrespectful to the environment, local residents, and the law.”

Google appealed, and a court hearing is scheduled for the new year.

Three days before the Belgian order, Judge Michael Doucette halted construction at another Google data center campus in Botetourt County, Virginia. Doucette ruled Nov. 23 that county supervisors violated Virginia’s Freedom of Information Act when they added Google’s performance agreement to the agenda during a June 2025 meeting and approved it 5-0 without discussion.

The judge voided the county’s subsequent actions and ordered a new public hearing. “‘Magic words’ must be used and ‘technical violations’ are not excused,” Doucette wrote.

The cases involve different local barriers. Wallonia revoked an amended environmental permit over water use and drought risk, while the Virginia project faced a court challenge to the process used to approve its agreement.

The European Union has proposed measures to increase data center capacity and create acceleration zones where permit decisions would take no longer than 12 months. EU telecom ministers are scheduled to consider the Cloud and AI Development Act on Dec. 1.

In the United States, federal policy favors faster AI infrastructure development, but state and local governments retain authority over data center siting. Botetourt County must hold a new public hearing before it can revive its agreement with Google.