PJM Calls on Demand Response for Oct. 13-14 as DOE Order Runs Through Oct. 16 PJM’s updated forecast put Oct. 14 load at 113,312 megawatts, while backup generation at large electricity users remained unused as of that day’s update.
Oct 15, 2026, 9:41 PM EDT · Regulation
PJM Declares Grid Emergency With 60 Gigawatts Offline The operator’s Western hub spot price reached $1,021 per megawatt-hour Tuesday, while Wednesday’s day-ahead average rose 28%.
Oct 14, 2026, 12:52 PM EDT · Technology
Energy Department Directs PJM Unit Dispatch, Authorizes Backup Resources The order covers Oct. 13–16 as PJM forecasts demand of at least 111,500 megawatts and expects about 61,591 megawatts of generation outages.
Oct 13, 2026, 12:56 PM EDT · Regulation