AUO Says Handover Date for Two-Plant Sale to TSMC Remains Unset

TSMC-invested 精材 is expected to build and operate advanced-packaging lines under a seven-year agreement, with first-phase production targeted for 2029.

A semiconductor plant stretches across a quiet industrial road / TokenPost.ai
A semiconductor plant stretches across a quiet industrial road / TokenPost.ai

Taiwan Semiconductor Manufacturing Co. (TSMC) is planning to turn AUO’s L7 and L5C plants in central Taiwan into an advanced-packaging hub and may retain about one-third of their workers to support advanced-packaging development.

AUO previously sold the two facilities to TSMC. Handover requires statutory procedures and regulatory approval. AUO’s spokesperson said Nov. 15 that a timetable has not been set.

Unnamed sources said TSMC is seeking to retain about one-third of the staff after AUO employees complete the voluntary retirement process. The workers’ experience would help advance packaging development. AUO employees said existing production must move to other sites and new lines need customer certification before the transition can be completed.

Those employees expect L5C to stop production in April 2027 and said L7 is planned to stop in September 2027. L7 is a 7.5-generation plant, while L5C is a fifth-generation facility.

TSMC-invested 精材 is expected to lead construction and operation of the back-end packaging lines under a seven-year capacity outsourcing agreement. 精材 plans to invest in equipment and automated material-handling systems and manage production and related operations. The company also plans to raise funds through corporate bonds for equipment and facility costs.

TSMC is expected to use the facilities to develop CoPoS, a panel-level advanced-packaging technology involving glass substrates. AUO has worked on glass processing for advanced packaging, including redistribution layers (RDL) and through-glass vias (TGV). AUO Chairman 彭双浪 has previously cited the company’s glass-processing experience and its capabilities in RDL and TGV.

The companies have not detailed a possible CoPoS collaboration. The first production phase at the new hub is targeted for 2029.