Google Takes Over Crusoe’s Unfinished Wyoming Data Center Project

Crusoe confirmed the sale on Nov. 6. Google plans a $17 billion campus investment, and the sale price was not disclosed.

Unfinished data center buildings stretch across a Wyoming prairie / TokenPost.ai
Unfinished data center buildings stretch across a Wyoming prairie / TokenPost.ai

Google is taking over an unfinished data center project in southeastern Wyoming after Crusoe confirmed Friday, Nov. 6, that it had sold the project. Google plans to invest $17 billion in the campus.

The sale price was not disclosed. Crusoe had initially sought Google as a customer for the site; Google is now taking over its development. The company’s previously announced $17 billion Wyoming data center plan included covering all electricity costs for the facility.

A separate proposed 702-megawatt fuel-cell project near Cheyenne was planned to supply some of that power under a 20-year agreement. American Electric Power has planned about $4 billion for the project.

Crusoe and Tallgrass announced the data center project last year, with plans to expand its power capacity to as much as 10 gigawatts. Crusoe began as a cryptocurrency mining business powered by natural gas that otherwise would have been burned off. It is also developing another data center for Google near Amarillo, Texas.