Elon Musk Says Colossus 2 Gains Nearly 1 GW From TVA Grid

The 500-kilovolt connection adds grid capacity to the Memphis-area AI data center, which also uses natural gas turbines.

Transmission towers lead toward an industrial data center campus / TokenPost.ai
Transmission towers lead toward an industrial data center campus / TokenPost.ai

Elon Musk said Colossus 2, an AI training data center associated with his AI operations in the Memphis area, has connected to the Tennessee Valley Authority (TVA) grid through a 500-kilovolt link that adds nearly one gigawatt of power.

The grid connection expands the site’s power supply but does not replace its existing generation. Colossus 2 still uses natural gas turbines with capacity of up to about 1.24 gigawatts, along with smaller connections through TVA and Memphis Light, Gas and Water.

The site also depends on a dedicated natural gas plant in Southaven. The combination of on-site generation and grid access gives the facility multiple sources of electricity as its computing infrastructure expands.

Colossus 2 uses Nvidia’s Blackwell-generation GB200 and GB300 GPUs. A previous filing detailing the phased Colossus 2 expansion described a second cluster of 110,000 GB300 processors and 220 megawatts of compute power brought online in 64 days.

The new TVA connection marks a further expansion of the facility’s power infrastructure.