Elon Musk Says Colossus 2 Gains Nearly 1 GW From TVA Grid
The 500-kilovolt connection adds grid capacity to the Memphis-area AI data center, which also uses natural gas turbines.

Elon Musk said Colossus 2, an AI training data center associated with his AI operations in the Memphis area, has connected to the Tennessee Valley Authority (TVA) grid through a 500-kilovolt link that adds nearly one gigawatt of power.
The grid connection expands the site’s power supply but does not replace its existing generation. Colossus 2 still uses natural gas turbines with capacity of up to about 1.24 gigawatts, along with smaller connections through TVA and Memphis Light, Gas and Water.
The site also depends on a dedicated natural gas plant in Southaven. The combination of on-site generation and grid access gives the facility multiple sources of electricity as its computing infrastructure expands.
Colossus 2 uses Nvidia’s Blackwell-generation GB200 and GB300 GPUs. A previous filing detailing the phased Colossus 2 expansion described a second cluster of 110,000 GB300 processors and 220 megawatts of compute power brought online in 64 days.
The new TVA connection marks a further expansion of the facility’s power infrastructure.